2013年11月30日星期六

PMI PMI-SP exam study materials

ITCertKing promise that we will spare no effort to help you pass PMI certification PMI-SP exam. Now you can free download part of practice questions and answers of PMI certification PMI-SP exam on ITCertKing. When you select ITCertKing, you can not only pass PMI certification PMI-SP exam, but also have one year free update service. ITCertKing can also promise if you fail to pass the exam, ITCertKing will 100% refund.

If you do not know how to pass the exam more effectively, I'll give you a suggestion is to choose a good training site. This can play a multiplier effect. ITCertKing site has always been committed to provide candidates with a real PMI PMI-SP certification exam training materials. The ITCertKing PMI PMI-SP Certification Exam software are authorized products by vendors, it is wide coverage, and can save you a lot of time and effort.

The quality of ITCertKing product is very good and also have the fastest update rate. If you purchase the training materials we provide, you can pass PMI certification PMI-SP exam successfully.

In this competitive IT industry, having some authentication certificate can help you promote job position. Many companies that take a job promotion or increase salary for you will refer to how many gold content your authentication certificates have. PMI PMI-SP is a high gold content certification exam. PMI PMI-SP authentication certificate can meet many IT employees' needs. ITCertKing can provide you with PMI certification PMI-SP exam targeted training. You can free download ITCertKing's trial version of raining tools and some exercises and answers about PMI certification PMI-SP exam as a try.

Exam Code: PMI-SP
Exam Name: PMI (PMI Scheduling Professional)
One year free update, No help, Full refund!
Total Q&A: 326 Questions and Answers
Last Update: 2013-11-30

The curtain of life stage may be opened at any time, the key is that you are willing to show, or choose to avoid. Most of People who can seize the opportunityin front of them are successful. So you have to seize this opportunity of ITCertKing. Only with it can you show your skills. ITCertKing PMI PMI-SP exam training materials is the most effective way to pass the certification exam. With this certification, you will achieve your dreams, and become successful.

PMI-SP Free Demo Download: http://www.itcertking.com/PMI-SP_exam.html

NO.1 You work as a project manager for BlueWell Inc. Management has asked you not to communicate
performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you
create for management, if these instances develop in your project?
A. Cost variance report
B. Exceptions report
C. Performance management report
D. Schedule variance report
Answer: B

PMI exam prep   PMI-SP   PMI-SP   PMI-SP dumps

NO.2 You are the project manager of the GHT Project. Ben, one of your project team members, does not
understand the idea of a milestone. Which of the following best describes what a milestone is?
A. A significant point in the project
B. A goal of reaching a significant delivery of project benefits by an identified date
C. An imposed date for the project to reach a given point
D. The completion of a project activity that is crucial to project completion
Answer: A

PMI pdf   PMI-SP exam prep   PMI-SP   PMI-SP questions   PMI-SP certification training

NO.3 CORRECT TEXT
Fill in the blank with an appropriate phrase.
The __________ includes a description of any collateral services required, such as performancereporting
or post-project operational support for the procured item.
Answer: procurement SOW

PMI demo   PMI-SP practice test   PMI-SP   PMI-SP practice test   PMI-SP   PMI-SP

NO.4 You are the project manager of the HQQ Project. Your project is running late by ten percent of where
you should be at this time. Management is concerned. Considering that the project has a BAC of
$567,899, you are thirty percent complete, and you have spent $179,450. What is this project's
to-complete performance index based on the current BAC?
A. 1.02
B. 0.010
C. 0.75
D. 0.95
Answer: A

PMI test   PMI-SP   PMI-SP   PMI-SP   PMI-SP exam prep

NO.5 George is the project manager of the NHQ Project and has a budget of $778,000. The project is
scheduled to last for one year with an equal amount of work completed each quarter. The second quarter
of the project has ended and George has spent $325,000 but has only finished forty percent of the project.
Management needs a variance report for the project schedule. What value should George report in this
instance?
A. .96
B. -$77,800
C. $-34,500
D. -$13,800
Answer: B

PMI   PMI-SP pdf   PMI-SP   PMI-SP study guide   PMI-SP test answers   PMI-SP test questions

NO.6 Gina is the project manager for her organization and she is working with her project team to define the
project activities. In this project, the stakeholders are sensitive to the project completion date,
so Gina is stressing to her project team members that while they need to provide and account for all of the
project activities, they should focus on one work package in the WBS at a time. In order to start the
decomposition of the project work packages into activities, Gina will need all of the following except for
which one?
A. Scope baseline
B. Organizational process assets
C. WBS
D. Enterprise environmental factors
Answer: C

PMI   PMI-SP   PMI-SP answers real questions   PMI-SP braindump   PMI-SP exam

NO.7 You are the project manager for your company. You are working with the activities defined in the figure
below.
What will happen to your project if Activity F takes five additional days to complete than what was
expected?
A. Your project's critical path will shift to ACFI.
B. Your project will be late by five days.
C. Your project can still complete on time as float is available onActivity I.
D. Your project will now have two critical paths.
Answer: B

PMI dumps   PMI-SP original questions   PMI-SP   PMI-SP   PMI-SP

NO.8 Sam is the project manager of the NQQ project. He and the project team have completed the
stakeholder identification process for his project. What is the main output of the identify stakeholders
process?
A. Communications management plan
B. Stakeholder register
C. Requirements
D. Stakeholder management strategy
Answer: B

PMI   PMI-SP certification   PMI-SP test questions   PMI-SP certification

NO.9 Ben is the project manager for his organization. His project has 26 stakeholders this week and will
have five additional stakeholders next week. How many more communication channels will Ben's project
have next week?
A. 140
B. 10
C. 325
D. 5
Answer: A

PMI   PMI-SP braindump   PMI-SP dumps   PMI-SP

NO.10 Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project.
There are eight tools and techniques that a project manager can use to develop the project schedule.
Which of the following is a tool and technique for the Schedule Development process?
A. Schedule compression
B. Reserve analysis
C. Variance analysis
D. Expert judgment
Answer: A

PMI exam simulations   PMI-SP   PMI-SP   PMI-SP

NO.11 Which of the following scheduling techniques identifies the successor activities and the
predecessor activities to assist the project manager in sequencing the project work?
A. Precedence Diagramming Method
B. Schedule network template
C. Dependency determination
D. Activity on the Node
Answer: A

PMI dumps   PMI-SP   PMI-SP   PMI-SP

NO.12 Once the project's WBS has been created what process may happen next?
A. Estimate activity resources
B. Define activities
C. Estimate activity durations
D. Sequence activities
Answer: B

PMI   PMI-SP   PMI-SP original questions   PMI-SP dumps

NO.13 The Define Activities process is the first process in the project time management knowledge are a.
The Define Activities process creates just three outputs as a result of decomposition, rolling wave
planning, templates, and expert judgment. Which one of the following is not an output of the Define
Activities process?
A. Activity list
B. Milestone list
C. Activity attributes
D. Project document updates
Answer: D

PMI   PMI-SP   PMI-SP exam   PMI-SP answers real questions

NO.14 You are the project manager of the GHY Project. Management wants you to create a process
improvement plan for your project. Your project will be studied by management and will become a
standard for all future organizational projects based on your project's performance, approach, and
implementation of project processes. All of the following should be included in your project's process
improvement plan except for which one?
A. Process boundaries
B. Process configuration
C. Targets for improved performance
D. Identification of project risks
Answer: D

PMI   PMI-SP questions   PMI-SP practice test   PMI-SP exam

NO.15 You are the project manager of the NHA Project. This project is expected to last one year with quarterly
milestones throughout the year. Your project is supposed to be at the third milestone today but you're
likely only 60 percent complete. Your project has a BAC of $745,000 and you've spent $440,000 of the
budget-to-date. What is your schedule performance index for this project?
A. 80
B. 1.02
C. 102
D. 0.80
Answer: D

PMI pdf   PMI-SP   PMI-SP   PMI-SP dumps

NO.16 You have created the project network diagram for the ABC project. You are exploring total float and
free float for that project. Martin, a project team member, wants to know the difference between total float
and free float. What is the difference between total float and free float?
A. Total float is the amount of time an activity can be delayed without delaying any project
successors, whereas free float is the amount of time an activity can be delayed without delaying the
project completion date.
B. Total float is the amount of time an activity can be delayed without delaying the project
completiondate, whereas free float is the amount of time an activity can be delayed without delaying any
project successors.
C. Total float is the amount of time an activity can be delayed without delaying the project
completiondate, whereas free float is the amount of time an activity can be delayed without delaying any
project predecessors.
D. Total float is the amount of time a non-critical activity can be delayed without delaying any project
successors, whereas free float is the amount of time an activity can be delayed without delaying the
project completion date.
Answer: B

PMI   PMI-SP   PMI-SP exam prep   PMI-SP

NO.17 You are the project manager for your organization. You need the oak cabinets for your project
delivered by December 1 in order to install the floors around the oak cabinets by December 15.
Your company's procurement office generally takes 45 days to complete procurement orders. Based on
this information, how should you schedule the lead time for the cabinet delivery?
A. Cabinet procurement December 1, plus 45 days lead time
B. Cabinet procurement November 15
C. Cabinet procurement December 1, minus 45 dayslead time
D. Cabinet procurement December 15 minus 45 dayslead time
Answer: C

PMI questions   PMI-SP dumps   PMI-SP   PMI-SP   PMI-SP certification training

NO.18 You are the project manager for your organization. You have recorded the following duration estimates
for an activity in your project: optimistic 20, most likely 45, pessimistic 90. What time will you record for
this activity?
A. 48
B. 20o, 45m, 90p
C. 90
D. 45
Answer: A

PMI   PMI-SP   PMI-SP   PMI-SP test

NO.19 John works as a project manager of the NHQ Project. He has created the project network diagram as
shown in the figure:
Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by
four days and Activity E is delayed by two days?
A. Zero
B. One
C. Four
D. Five
Answer: A

PMI demo   PMI-SP dumps   PMI-SP answers real questions   PMI-SP braindump

NO.20 Your project team is executing the project plan and things are going well. Your team has reached
its first milestone and is now in the second phase of the project. The project stakeholders have requested
that you find a method to reduce the duration of the project. They will reward you and your project team
with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was
already planned. The stakeholders, however, will not approve any additional labor costs as part of the
agreement. Which approach could you use to shorten the duration of the project?
A. Perform resource leveling for the project.
B. Crash the project schedule.
C. Fast track the project.
D. Remove things from the project scope.
Answer: C

PMI demo   PMI-SP certification training   PMI-SP   PMI-SP exam   PMI-SP

NO.21 Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however, your
project should actually be 80 percent complete. You have spent $575,000 of your project budget to reach
this point and you are worried about the project not being able to complete based on your current project
budget. What is the to-complete performance index for this project?
A. 0.98
B. -$16,677
C. 1.07
D. 0.94
Answer: C

PMI   PMI-SP   PMI-SP   PMI-SP

NO.22 You are the project manager of the NHQ Project. You have created the project network diagram as
shown in the figure:
You are concerned about a risk on Activity G that if it happens will delay the project by four days.
You would like to utilize float for Activity G. How much float is available for Activity G to help offset the risk
event?
A. Five days
B. Four days
C. Eleven days
D. Zero
Answer: D

PMI   PMI-SP   PMI-SP exam simulations   PMI-SP questions

NO.23 You are the project manager of the NHGQ project for your company. You must create and distribute
performance reports every week to your key project stakeholders. What communication technique do you
normally use to distribute reports?
A. Push technique
B. Many-to-many
C. One-to-one
D. Pull technique
Answer: A

PMI study guide   PMI-SP exam   PMI-SP exam dumps   PMI-SP

NO.24 You are the project manager of the BHG Project. You are creating a network diagram as shown in the
figure:
Mary, a project team member, reports that an identified risk is likely to happen in the project that will affect
the completion date of Activity D . She reports that the risk event will likely cause the duration of the
activity to increase by six days. If this happens what is the earliest the project can complete?
A. 32 days
B. 29 days
C. 27 days
D. 26 days
Answer: D

PMI   PMI-SP   PMI-SP   PMI-SP exam dumps   PMI-SP demo

NO.25 Which one of the following estimate types is a form of expert judgment?
A. Parametric estimate
B. Analogous estimate
C. Bottom-up estimate
D. Definitive estimate
Answer: B

PMI   PMI-SP original questions   PMI-SP certification   PMI-SP questions

NO.26 You are the project manager of the NHQ Project. Management has set a conformance to the project
schedule for your project at 0.95. What does this term mean?
A. It means the largest schedule variance you can have is five percent.
B. It is the earned value divided by the planned value for your project.
C. It is the expectation of management to be 95 on schedule at 95 percent of the project.
D. It means you will need to earn at least 95 cents per dollar invested in the project.
Answer: A

PMI test answers   PMI-SP test questions   PMI-SP questions   PMI-SP   PMI-SP study guide

NO.27 Mark is the project manager of the GHQ Project. He is happily reporting that his project has a schedule
performance index of 2.12. Management, however, does not think this is good news.
What is the most likely reason why management does not like an SPI of 2.12?
A. It is not good news because a larger number means the schedule duration estimates were likely to be
wrong to begin with.
B. They likely do not understand the SPI formula.
C. It is not good news, as the number should be closer to 100 than 0.
D. It is good news, but Mark may have large cost variances to achieve this value.
Answer: A

PMI   PMI-SP practice test   PMI-SP   PMI-SP

NO.28 Examine the figure given below:
If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay
Activity H?
A. Three days
B. One day
C. Four days
D. Zero days
Answer: B

PMI   PMI-SP questions   PMI-SP exam prep   PMI-SP exam prep

NO.29 CORRECT TEXT
Fill in the blank with the appropriate word. When activities are logically linked, they become the
__________
Answer: Schedule.

NO.30 Beth is the project manager for her organization. Her current project has many deliverables that have
been defined at a high level, but the details of the deliverables are still unknown. In her project, Beth is
planning in detail only the activities that are most imminent in the project work. This approach to project
management planning is known as what?
A. Imminent activity management
B. Rolling wave planning
C. Predecessor-only diagramming
D. Decomposition
Answer: B

PMI   PMI-SP exam prep   PMI-SP   PMI-SP   PMI-SP

ITCertKing offer the latest HP2-B102 exam material and high-quality 70-466 pdf questions & answers. Our 700-505 VCE testing engine and HP2-E58 study guide can help you pass the real exam. High-quality NS0-504 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.

Article Link: http://www.itcertking.com/PMI-SP_exam.html

没有评论:

发表评论